Hi SAP Gurus ,
We have a scenario were our client owns Fleet of buses across various states in a country and each state has its own buses and bus workshops.
So every state has its own planning plant and maintenance plant .
· State ‘A” =Planning plant =1000 and Maintenance Plant=1000
· State B = Planning plant =2000 and Maintenance Plant=2000
The Maintenance Plans are created and scheduled at each state level.
As these Buses are mobile , if PM02 maintenance order date is due for Bus of state A and the Bus belonging to state “A” has now travelled to state “B” .
Then state “B” workshop picks up this bus and executes the planned maintenance work on it.
State B , uses the all the materials required for Planned maintenance from its own plant stores (Plant 2000)
Now since the Equipment , Plan , Task list , Maintenance order, reservations are generated on Plant 1000 but are executed by maintenance team / material from Plant 2000.
How can I map this process in SAP , so that Maintenance work planned by one depot is executed by another depot?
Thanks
Frazer