Hi SAP Daya,
Is this a planned order for inhouse production?
In this case, the difference between the production end date and the date in which the component are required comes from the routing and not the delivery date. Note that the requirement date is the production start date..
In your case it seems the order starts in Oct 12nd.. which is in the past...
Does it explain your problem?
Kind Regards,
Mariano